Connect Logistics is building a 9 acre warehouse and cold storage facility at Tarnol, on Main Fateh Jang Road in District Attock. Phase 1 will deliver 16,000 pallet positions, split evenly between temperature controlled storage and racked ambient, with a target opening in Quarter 2 of 2027.
Connect Logistics is building its first warehouse in the Islamabad region. The site sits at Tarnol, on Main Fateh Jang Road in District Attock, and it will be our fifth city and our first facility in the north of the country.
For seventeen years our network has grown outward from Karachi, through Lahore, Multan and Khairpur, to the 119,000 pallet positions we operate today. Every one of those facilities was built rather than rented, because owning the building is what lets us hold a standard in it. Islamabad follows the same principle, and it closes the one gap our clients have asked about most often: dependable, purpose built, temperature controlled storage serving the Federal Capital, north Punjab and the corridor into Khyber Pakhtunkhwa.
This post is our first public update on the project. We will keep it current as the structure goes up, so if you are planning northern capacity for 2027 it is worth bookmarking.
The project at a glance
Phase 1 will deliver 16,000 pallet positions, roughly the equivalent of 800 forty foot containers of storage, split evenly between temperature controlled and ambient. The nine acre plot has been laid out so that the remaining capacity, taking the site to 40,000 pallet positions in total, can be added in later phases without disturbing live operations.
What Phase 1 will hold
−25°C to +18°C
Purpose built chambers covering the full range from deep frozen through chilled to controlled ambient, so frozen food, ice cream, dairy, pharmaceutical and other temperature sensitive product can all be held on one site at their own set points.
Racked dry storage
High bay racked ambient storage for FMCG, packaging, agrochemicals and general dry goods, designed to the same racking, aisle and material handling standards as the rest of our network.
Both halls will be operated on the same systems our other sites run on, so a client already storing with us in Karachi or Lahore will see the same inventory visibility, the same batch and lot traceability and the same reporting when Islamabad comes online.
Why Tarnol
Tarnol sits on the western approach to Islamabad, on the corridor that carries traffic between the capital, Attock, Peshawar and the north. For a warehouse that is the point. Product can reach Rawalpindi and Islamabad, move north into Khyber Pakhtunkhwa, or run south down the motorway network towards Lahore and onward, without threading through city centre congestion first.
The land is nine acres, which is what gives the project its headroom. It is enough for the Phase 1 buildings, the yard and dock apron they need, and the later phases that take the site to 40,000 pallet positions, all on one title and under one perimeter.
Open the site location in Google Maps
How Islamabad fits the national network
Connect Logistics currently operates 119,000 pallet positions, approximately 6,000 forty foot containers of storage, across four cities. Islamabad becomes the fifth.
| Site | Ambient | Temperature controlled | Total pallet positions |
|---|---|---|---|
| Karachi | 35,000 | 27,000 | 62,000 |
| Lahore | 2,000 | 31,000 | 33,000 |
| Multan | 7,500 | 4,500 | 12,000 |
| Khairpur | 12,000 | – | 12,000 |
| Islamabad, Tarnol Phase 1, planned | 8,000 | 8,000 | 16,000 |
On completion of Phase 1 the network will stand at 135,000 pallet positions nationally, with the Islamabad site holding room to grow to 40,000 on its own.
Where the project stands
- Land and layoutThe nine acre site at Tarnol has been secured and the master plan set out, fixing the position of the Phase 1 buildings, the dock apron, the yard circulation and the later phases.
- Civil works and foundationsSite preparation, foundations and the floor slab, which for a racked warehouse is the single most exacting element of the build.
- Structure and envelopeSteel frame erection followed by roof and wall cladding, with insulated panel construction on the temperature controlled chambers.
- Refrigeration and fit outInstallation of the refrigeration plant, racking, docks, dock levellers, power backup and the monitoring and security systems.
- Commissioning and handoverTemperature mapping and validation of the chambers, systems testing and staff onboarding ahead of the target opening in Quarter 2 of 2027.
Planning northern capacity for 2027
If Islamabad is on your own roadmap, the useful thing to know now is that Phase 1 capacity is finite and that we plan allocations well ahead of opening. Clients who tell us early what they will need, how much of it is frozen, chilled or ambient, and roughly when they want to start, get factored into the commissioning schedule rather than joining a queue after handover.
In the meantime, our existing network is live and has capacity today. Cold storage in Pakistan and our facilities cover what is available right now across Karachi, Lahore, Multan and Khairpur.
Frequently asked questions
When will the Islamabad warehouse open?
Where exactly is the facility located?
How much storage will be available?
What temperatures will the cold storage hold?
Can I reserve space before the facility opens?
Where can I store in the north until Islamabad opens?
Register your interest in Islamabad
Tell us what you expect to store, at what temperature and from when. We will keep you on the list as Phase 1 capacity is allocated, and let you know when the facility is ready for site visits.
Register your interestLooking for capacity today? See our operating facilities.Figures on this page describe a facility under construction and are planned rather than operational. They will be confirmed and updated as the build progresses towards the Quarter 2, 2027 target opening.